Commercial solar in 2026: the new 100 kW to 1 MW rules, and choosing an installer
The short answer
Business systems up to 100 kW earn up-front STCs as usual. From 1 October 2026, systems over 100 kW and up to 1 MW can also earn STCs up front, based on a fixed 5 years of output every year to 2030, or choose Guarantee of Origin (REGO) certificates instead. Applications for mid-scale systems open in mid to late November 2026. Systems over 1 MW follow the large-scale certificate (LGC) route.
Three size bands
| System size | Scheme | How it works |
|---|---|---|
| Up to 100 kW | Small-scale STCs | Up-front certificates on systems up to 100 kW, applied as a discount by your installer. The deeming period shortens each 1 January until 2030. |
| 100 kW – 1 MW | Mid-scale STCs | From 1 October 2026, systems over 100 kW and up to 1 MW earn five years of STCs up front, fixed through 2030. Needs documented network and planning approvals. Alternatively, you can opt into Guarantee of Origin certificates. |
| Over 1 MW | Large-scale certificates | Systems over 1 MW can be accredited as a power station and earn one large-scale certificate (LGC) per MWh generated, or Guarantee of Origin certificates. They receive no STCs. |
What changes for mid-scale solar from 1 October 2026?
From 1 October 2026, systems over 100 kW and up to 1 MW have their own mid-scale path:
- Eligible: systems over 100 kW and up to 1 MW installed from 1 October 2026. “Installed” means first able to produce electricity, which is the commissioning date on the electrical compliance certificate.
- Up-front certificates: STCs for 5 years of deemed output, fixed at that length each year to 2030. Small systems, by contrast, lose a year of deeming every January (5 years in 2026).
- Or ongoing certificates: you can choose REGO certificates under the Guarantee of Origin scheme instead. If you take STCs, you can't also create REGO certificates for the deeming period.
- Evidence: planning and network connection approvals, engineering reports and a written installer statement, with approved components and an SAA-accredited installer.
- The 1 MW cap counts related systems: adjacent or related systems on the same site, including existing ones, count towards it. Extending an existing system earns STCs on the new capacity only.
- Timing: applications open in mid to late November 2026; systems installed from 1 October are assessed under the rules at that date.
| System | Installed in 2026 | Installed in 2027 |
|---|---|---|
| 99 kW (small-scale) | $25,308 684 STCs | $20,239 547 STCs |
| 200 kW (mid-scale) | $51,134 1,382 STCs | $51,134 1,382 STCs |
| 500 kW (mid-scale) | $127,835 3,455 STCs | $127,835 3,455 STCs |
These are our estimates using the regulator's zone ratings. The Clean Energy Regulator's calculator gives the exact entitlement. Note the effect of the fixed deeming period: from 2027, a mid-scale system is credited for more years of output than a small one.
How does a larger system get connected to the grid?
Larger systems need your network's approval before they're built. Under the national connection guidelines, basic connections go up to 30 kVA three-phase, with exports usually limited to around 5 kVA per phase. Above that, the network sets export limits case by case, you pay for any technical studies, and an engineer signs off commissioning. Allow time and budget for this, and get the network's requirements in writing early, including any change to your tariff.
What size commercial solar system do you need?
Size business solar to your load, not your roof: it pays back fastest when you use most of what it produces. Your electricity interval data (the half-hourly readings from your meter, often called NEM12) shows when you use power and what your demand charges are. A good installer designs from that data, not from a single bill. Batteries can also reduce demand charges, and NSW has business battery incentives (BESS4 and BESS5) that stack with the federal discount. Our business assessment starts from your data.
How do you choose a commercial solar installer?
When you choose a commercial solar installer, check:
- SAA accreditation, current electrical licences, and a track record on systems of similar size (ask for references you can call)
- Who does the work: in-house teams or subcontractors
- A design based on your interval data, with expected generation, self-consumption and savings, and the assumptions behind them
- Network approval handled and costed up front, plus building and structural approvals where needed
- Performance guarantees, monitoring (who watches it, and what happens when output drops), and a written maintenance agreement
- Product and workmanship warranties, handover documents, an operations manual and training for your staff
Buy it, or sign a power purchase agreement?
With a power purchase agreement (PPA), a provider installs and owns the system and you buy its electricity at an agreed rate, usually over 10 to 15 years. No capital outlay, but often more expensive overall than buying. Check how the rate rises each year, who gets the export credits, whether you pay for all generation or only what you use, who maintains the system, and what it costs to exit early or if you sell the building.
Questions people ask
Can businesses get STCs for solar over 100 kW?
Yes, from 1 October 2026. Systems over 100 kW and up to 1 MW can earn STCs up front for 5 years of deemed output, or choose Guarantee of Origin (REGO) certificates instead.
When do mid-scale STC applications open?
Mid to late November 2026, for systems installed from 1 October 2026. Installed means the commissioning date on the electrical compliance certificate.
What happens above 1 MW?
Systems over 1 MW are accredited as power stations under the large-scale scheme and earn large-scale generation certificates (LGCs) until the scheme ends in 2030, or Guarantee of Origin certificates.
Do I need network approval for commercial solar?
Yes. Connections above the basic 30 kVA three-phase category are assessed by your network, which sets export limits, may require technical studies at your cost, and needs engineer sign-off at commissioning.
Is a solar PPA better than buying?
It avoids the upfront cost but is often more expensive over the term. Compare the rate and its escalation, export credits, maintenance and exit terms against buying outright.
Sources
- Clean Energy Regulator: Expansion of solar PV eligibility under the SRES (August 2026)
- Clean Energy Regulator: Mid-scale solar
- Clean Energy Regulator: Renewable Electricity Guarantee of Origin
- DCCEEW: Renewable Energy Target scheme
- Energy Networks Australia: DER connection guidelines FAQ
- energy.gov.au: Loans and finance for commercial organisations (PPAs)
General information, not financial advice. Rebate rules change: figures on this page come from our rules table, last verified 26 September 2026. How we're paid: installers pay Homerise for introducing you. No brand or installer pays to be mentioned in a guide.